Project Outline

Eco Tiffin were instructed to investigate persistent dampness affecting the rear hallway and WC of a residential property in Cheddington, Bedfordshire.

The homeowner had experienced ongoing moisture issues following a historic escape of water beneath the kitchen and was concerned that the dampness was continuing despite the leak having been repaired.

Our inspection identified that while the previous leak had contributed to elevated moisture levels, the principal ongoing issue was the external ground levels, which had been raised over time and were now bridging the property’s original damp proof course.

Rather than recommending unnecessary damp-proofing treatments, we identified the true cause of the problem and specified a long-term drainage solution.

The Challenge

The property had experienced a concealed leak from the incoming stopcock behind the kitchen units approximately 18 months before our inspection.

Although the plumbing defect had been repaired, moisture remained present within the solid concrete floor of the rear hallway.

Externally, later patio works had significantly increased the external ground levels, leaving the paving too close to the internal floor level and original damp proof course.

This combination of historic moisture together with poor external drainage was preventing the structure from drying naturally and increasing moisture loading to the base of the walls.

Our Investigation & Findings

Our survey included moisture profiling, visual inspection and assessment of the property’s construction.

The investigation established that:

  • The previous plumbing leak had been repaired and was no longer active.
  • Moisture readings within the adjoining walls were generally acceptable.
  • Elevated moisture remained within the exposed concrete floor due to historic wetting.
  • Raised external patio levels were bridging the original damp proof course.
  • Rainwater was collecting against the rear elevation because of insufficient drainage.
  • The elevated external moisture was increasing heat loss by keeping the wall base cold and saturated.

Rather than diagnosing rising damp, we concluded that the moisture problems were being sustained by external ground conditions and inadequate drainage.

Our Solution

Eco Tiffin recommended allowing the building to continue drying naturally following the repair of the plumbing leak while addressing the external moisture source.

To permanently reduce moisture loading, we specified the installation of the Eco Tiffin AirDrain system along the rear elevation.

The AirDrain system was designed to:

  • Reduce external moisture against the wall.
  • Prevent bridging of the damp proof course.
  • Improve evaporation at the base of the wall.
  • Reduce cold bridging and associated heat loss.
  • Improve the long-term moisture performance of the property.

This fabric-first approach addressed the cause of the problem rather than treating the symptoms.

Scope of Works Delivered

Eco Tiffin prepared a specification for:

  • Installation of the Eco Tiffin AirDrain system to the rear elevation.
  • Excavation adjacent to the property.
  • Installation of pea shingle drainage.
  • Provision for land drainage where required.
  • Protection of existing paving and external finishes.
  • Full site preliminaries and project supervision.

The Outcome

This project demonstrates the importance of carrying out a detailed building investigation before recommending damp-proofing treatments.

Rather than simply installing a chemical damp proof course, Eco Tiffin identified the underlying causes of the moisture and developed a solution that addressed both dampness and energy efficiency.

By combining moisture investigation with an understanding of building physics, we were able to recommend a permanent solution that reduces moisture ingress, improves drying potential and helps lower future heat loss.

The result is a property better protected against the effects of increasing rainfall while preserving the original building fabric.

Share

Related Case Studies

See more of our work below.

AWARD WINNING COMPANY

Badge stating Eco Tiffin were finalists for the SME National Business Awards 2021
Master Builder Awards badge, Highly Commended, Medium Renovation Project, Southern Counties 2021, presented to Eco Tiffin Ltd
Property Care Association logo
Federation of Master Builders logo